Build Schedule
| Build | Dependencies | Design: Dates/Duration | Design: Assigned to | Code: Dates/Duration | Code: Assigned to | Test: Dates/Duration | Test: Assigned to |
|---|---|---|---|---|---|---|---|
| ASB-1 | None | UW-9 -> UW-11 (3 weeks) | Stephen & Gary | ||||
| ASB-2 | None | UW-9 -> UW-10 (2 weeks) | Amiel & Fan | ||||
| ASB-3 | ASB-1 | BW-1 -> BW-2 (2 weeks) | |||||
| ASB-4 | ASB-3 | BW-3 -> BW-4 (2 weeks) | |||||
| USB-1 | None | UW-9 -> UW-11 (3 weeks) | Eric & Shankar | ||||
| USB-2 | USB-1 | BW-1 -> BW-2 (2 weeks) | |||||
| USB-3 | None | BW-1 (1 week) | |||||
| USB-4 | ASB-4 | BW-5 -> UW-13 (2 weeks) | |||||
| USB-5 | USB-4 | UW-14 -> UW-15 (2 weeks) | |||||
| USB-6 | USB-4 | UW-14 -> UW-15 (2 weeks) |
- ASB-1 refer to "Admin System Build 1"
- USB-1 refer to "User System Build 1"
- UW-1 refer to the University Study Period "Week 1" (24 weeks, 12 weeks each semester)
- BW-1 refer to the mid-year Break "Week 1" (Mid-year break is approximately 6 weeks long)